Cougar® DC Truck Vibrators Deliver Cleaner Dumps Every Time
Products Used Cougar® DC Truck Vibrator
Product Types Used Vibration Solutions , Truck Vibrators
Industry Mining
Customer South-Africa, North West Province

Problem

Material stuck in the bin due to its sticky and abrasive nature, causing several operational challenges.

A chrome mine located in the North West province of South Africa was experiencing persistent and costly challenges with its dump trucks used for transporting sticky and abrasive chromite. After dumping, a substantial amount of material often remained stuck in the truck bin. This required manual intervention to clear the residual load - introducing both safety risks and operational delays. The incomplete dumping process not only reduced overall efficiency but also increased operational costs, as the mine was effectively paying for undelivered material. Additionally, the abrasive nature of the material led to frequent wear and tear of the bin liners, requiring regular replacements and adding to maintenance costs.

Solution

Installation of Cougar® DC Truck Vibrator

The customer initially attempted to resolve the issue using bin liners, however, the problem persisted. To address this, Martin Engineering’s specialists recommended a test installation of a 24V Cougar® DC Truck Vibrator to facilitate the complete discharge of the material. Rugged and economical, the Cougar® DC Truck Vibrator improves the speed and efficiency of unloading dump trucks. By energizing the load and breaking the friction between particles, the vibrator effectively mobilizes bulk material, allowing for faster and more thorough unloading. This means faster, more complete unloading - getting trucks back on the road more quickly and improving overall operational efficiency.

Result

Stuck material was eliminated - each truck is now fully emptied after unloading.

The installation of the Cougar® DC Truck Vibrator significantly improved material flow efficiency and greatly reduced the need for manual material handling. The truck has been operating with the same liners for over a year since installation, without the need for replacement. Thus the DC Truck Vibrator exceeded expectations, delivering multiple benefits including enhanced liner durability, substantial cost savings from reduced bin liner replacements, and a marked reduction in maintenance demands and manual intervention. Impressed by the results of the initial trial, the customer proceeded with the installation of an additional 50 units across the truck fleet.

We Solved Their Problems!
Let us help you solve yours as well. All products and services provided by Martin Engineering carry our Absolutely No Excuses Guarantee. If we don't solve your problem, we will fully refund your money or provide a different solution for you. Period.
Martin® Vibrating Dribble Chute prevents buildup on discharge chute walls
Hindustan Zinc Limited was experiencing severe amounts of buildup on conveyor 09 discharge chute walls transferring 100TPH zinc concentrate. To overcome this, plant managers had modified it with increasing the front gap and also tried using UHMW as well as improved SS liner plates having 2B finish. Still due to material moisture content (8-12%), material buildup issue had not been resolved, so the final solution in use was, deputing manpower for doing manual cleaning for every 8 hours. But such frequent manual cleaning was costlier and also risky considering worker's safety.
Read Case Study
Martin® Belt Cleaners reduced the amount of carry-back significantly and effectively at the Tata Steel Limited plant
The Tata Steel Limited plant in Eastern India had excessive amounts of carryback due to inadequate conveyor belt cleaning. Heated material stuck to the belt and by-passed the existing cleaner, spilling cargo along the entire belt return. Operators observed large amounts of build-up around the take-up pulley, where spillage would accumulate and encapsulate rollers. Rollers often seized, with the belt riding on abrasive material, which can reduce belt life.
Read Case Study
Martin® Air Cannons prevents shutdowns due to clogging issues
Harsco's steel plant customer in South Central India was experiencing serious clogging issues on a hopper chute leading to the main bulk conveying system. Conveying 1680 mt/d (1850 st/d) of raw iron ore, fines would collect on the walls, quickly build up, then rathole and eventually block the chute completely. The 24 hour operation would require 3 or more hours per day of downtime for clearing of the material.
Read Case Study

Resources

PDF - Printable Version of Case Study Download